Teams |
personnel |
Flow chart |
Lead time |
|---|---|---|---|
|
RFQ from customers |
VP, Sales, Engineer, QC |
1.Design confirmed |
2 days |
| ↓ | |||
| Design Engineer | VP, Engineer head, engineer, technician | 2.Feasibility | |
|
↓ If No Tooling, Skip to 5 |
|||
| 3.Tooling design, Circuitry design | |||
| ↓ |
5 wks Circuitry design 4-5wks |
||
|
Tooling ? |
VP, Engineer , purchasing, supplier | 4. Open tooling | |
|
Circuitry design EVT Reliability Test |
Engineer and the head | ↓ |
3wks 4wks |
| 5. Workmanship6. Circuit EVT | |||
| ↓ | |||
|
Safety Approval |
Safety Engineer, and the head |
Safety Agent |
4-6wks |